Transmission Rebuild

Hickory Grove, SC – Volt Power performed an eight-mile transmission rebuild. This consisted of constructing a temporary transmission line, followed by the demolition of the existing line, and then the construction of the new 115KV transmission line. Line construction was in rough terrain and was made up of both steel foundation structures and steel direct embedded structures. This along with ensuring connections to the existing substations, not to mention load transfers from the temporary feed to new line to complete the project.